Assignment Discounting
Task
The following series of cash flows is given:
t0 | t1 | t2 | t3 | t4 |
100 | 100 | 100 | 100 | 100 |
Calculate the present value (PV) if the interest rate is
- 10%
- 35%
Solution
- PV = 100 *1,1^0+ 100*1,1^-1+100*1,1^-2+100*1,1^-3+100*1,1^-4 = 416.99
- PV = 100*1,35^0 + 100*1,35^-1+100*1, 35^-2+100*1, 35^-3+100*1, 35^-4 = 299.69